Friday, October 31, 2008
Well the weather has finally turned. We have experienced a wonderful fall with all the colors to match the Northeast. The drive to the house site has been more colorful each night.
The guys have gotten more walls up now. Most of the NE side of the house is now framed in and standing. The bedroom exterior walls are done. Eazy to see the windows that will take up most of the two outside walls. Also to see the door to the outside shower and what the view of the standing timber from the bedroom will be like.
The den now has three sides and you can see the windows there and the windows in the quilt studio. It is clearly beginning to take recognizable shape.
Everyone take care.
The guys have gotten more walls up now. Most of the NE side of the house is now framed in and standing. The bedroom exterior walls are done. Eazy to see the windows that will take up most of the two outside walls. Also to see the door to the outside shower and what the view of the standing timber from the bedroom will be like.
The den now has three sides and you can see the windows there and the windows in the quilt studio. It is clearly beginning to take recognizable shape.
Everyone take care.
Wednesday, October 29, 2008
Walla! Walls
Peggy is going to be gone for a few days and we anticipate that a significant amount of visual change will take place while she is gone. Therefore I am being trained to try and update this when possible.
The walls that are up in the photos are of the master bedroom on the left, the entry between and the den to the right. The area next to the den will be the quilt studio. The area where the lumber is setting obviously is the garage.
Let us know your thoughts on how you see the progress. Always fun to hear from all of you.
Tuesday, October 28, 2008
Monday, October 20, 2008
Waiting for Walls
Yesterday was a beautiful day. Not much visable change in the house but a good day to dig in the dirt. We planted trees, shrubs and bulbs. Some of you have heard about our rock issue. Well the picture says it all. The house is setting to the left of this "rock" bank. Need any landscaping rock or maybe a fountain rock? We hadn't planned on having a fountain but I think it is now in our future. Ron has planted about 15 trees with more to go. The lines for the septic tank and well are done and the trenches are filled. The framing is scheduled to start this week. We have our fingers crossed.
Thursday, October 16, 2008
Decking
Monday, October 13, 2008
Slow Visual Progress
The second picture of taken looking back up the driveway. It's hard to see but Ron planted 12 Crimson Red Maple trees along the upper bank of the driveway. There are at least 15 trees to plant along with numerous bushes we aquired last spring. I'm also thinking it's time to get some daffodils.
We're excited at maybe seeing actual framing this week.
Thanks for looking.
Sunday, October 5, 2008
Rainy Days
There's not a lot of visual progress to see but forward momentum is good. The floor beams are in with some internal plumbing happening. Ron spent the day yesterday burning some of the brush we cleared during the summer. With the rain starting it's allowed him to safely burning. There is forest surrounding us.